              40     FINNISH WIND POWER







































            the cumulative wind power capacity   project developers and to plan and
            to total of 5,7 GW. According to the   build the grid beforehand. Even
            statistics of WindEurope, Finland   though Fingrid has speeded up their
            was one of the top three European   investment plans there is scarcity
            countries on capacity installed in   of grid availability in some parts of
            2022. Based on the investment    Finland.
            decisions made, it can be said that in
            2026 wind power will already cover   Thanks to rapid technological
            a third of the country's electricity   development, since 2017 wind power
            consumption.                     has been the cheapest electricity
                                             production method in Finland. The
            In the big picture one of the    wind speed in Finland is not as
            key drivers in the wind power    strong as for instance in the UK but
            development and green transition in   the project developers are allowed to
            Finland is the ambitious target to be   use the state-of-the-art technology
            carbon neutral by 2035. The target   that lowers the costs and makes
            means electrification of industry,   the projects feasible. In the planning
            heating, and transportation. In the   and permitting the future tip and
            winter 2023 Finland also set the   hub heights are used. For example,
            target to produce at least 10 % of the   in a spatial planning process that is
            EU’s hydrogen targets.           started today the tip height of 350
                                             meters is typically used.
            The brutal Russian war in Ukraine
            has also meant a need to increase   There is no such turbine in the
            the energy independence of Finland.   market yet. But it does not matter as
            Growing amount of clean electricity is   one is always allowed to construct a
            needed to fulfil these targets.   smaller turbine than defined in the
                                             spatial plan. The developer does not
            The keys to success              have to specify the actual turbine
            One important key to success has   type in the permitting either – it
            been the fact that Finland has got   is enough that the environmental
            one of the best TSOs in the Europe.   impacts of the chosen turbine type
            The TSO, Fingrid, is proactive and   does not exceed the ones defined in
            keen on having discussions with   the permit.